Heavy metal relocation: SIAD takes on WVA’s historic SX-55 rotary forge
By TIM UTT
Movement Division chief, SIAD Logistics Support Directorate
SIERRA ARMY DEPOT, Calif. – The decommissioning of a massive industrial asset is never just a matter of locking the doors. When Watervliet Arsenal retired its historic SX-55 rotary forge, it kicked off a monumental logistics and storage mission — one uniquely suited for the capabilities and expertise at Sierra Army Depot.
A legacy of firepower and SIAD’s advantage
For almost 50 years, the SX-55 rotary forge was a centerpiece of heavy manufacturing operations at WVA, the oldest continuously active arsenal in the United States. The massive, four-hammer GFM radial forging machine was instrumental in the automated forging of large-caliber armaments, most notably 155mm artillery gun tubes. The immense pressure and precision of the SX-55 ensured the absolute core density and structural integrity required for these critical weapon systems.
As part of a modernization project, this behemoth was dismantled and relocated piece-by-piece to its new home at SIAD. The mission officially kicked off when the first two pieces arrived on May 18.
Relocating nearly a million pounds of custom-crated, heavy industrial machinery requires a facility with specific capabilities. SIAD, the Army's premier facility for equipment retrograde and long-term storage, sits on 36,000 acres. Along with having plentiful outdoor storage capacity, SIAD's high desert environment averages less than five inches of precipitation annually. This unique climate allows metal equipment like the SX-55 components to be stored indefinitely with little-to-no risk of rust or corrosion.
Engineering the heavy lift
The sheer scale of the SX-55 presented immediate challenges for the SIAD field operations team. Early data from WVA revealed a massive hurdle on the horizon: while average pieces were heavy, there were four colossal components to be delivered — two weighing approximately 137,000 pounds each, and two at 136,000 pounds each.
SIAD employees quickly identified that the extreme dimensions and weights of the custom crates lacked visible lifting points and center-of-gravity markings. Proactive problem-solving kicked in. Reaching out to an industrial engineer at WVA, the SIAD team secured images and critical load data. From there, the chiefs of the Movement Division and North Movement Branch as well as senior crane operators began brainstorming and drafting detailed lift plans.
They quickly discovered that the four largest pieces would exceed the capacity and configuration limits of SIAD’s existing rigging equipment. Working closely with the SIAD program manager, the team successfully procured specialized belly slings of the proper length and capacity, alongside wide-mouth shackles designed to prevent sling binding, ensuring they were fully prepared for when the heaviest components would arrive.
By the end of July, SIAD had received a staggering number of components weighing more than 1,235,977 pounds. The heaviest piece received to date weighed 67,902 pounds, with depot personnel still awaiting the arrival of the four heaviest components.
Armed with the right gear and a meticulous plan, the SIAD team successfully offloaded all pieces received, setting them on cribbing without a single incident.
This flawless execution was a direct result of the subject matter expertise of SIAD’s Logistics Support Directorate and Movement and Transportation divisions, backed by dedicated supporting staff from the Storage Support Directorate, including riggers, ground guides and storage personnel. Together, they proved that no matter how heavy the lift, SIAD is ready to shoulder the load any day.